As a result, the completion date for the huge data-center cluster, consisting of about 260 megawatts of computing power that CoreWeave plans to lease to OpenAI, has been pushed back several months. There were additional delays caused by revisions to design plans for some of the data centers a partner is building for CoreWeave in Texas and elsewhere, according to filings.